Rehabilitation of a drinking and process water supply for two hydroelectric power plants in the Silvretta region, Vorarlberg

AEP was commissioned by illwerke vkw AG to rehabilitate the drinking and process water supply for the Obervermunt I and II hydroelectric power plants.

 

Services

Rehabilitation of the drinking and process water supply for the Obervermunt I and II hydroelectric power plants owned by the illwerke vkw AG.

  • Perform a variant study
  • Creation of a submission plan with subsequent tendering and awarding of all trades
  • Concretisation of a feasible execution plan
  • Complete technical and commercial construction supervision of the master builder works, plant construction and electronic I&C trades

Facts & Figures

Company

AEP Planung und Beratung GmbH

Completion

2020

Area of expertise

Water + Environment

Construction style

Rehabilitation

Construction type

Supply systems

Work carried out

New construction of elevated + spring collection tanks, reconstruction of spring water reservoirs, rehabilitation of the pump station, conversion of distribution structures, construction of a control system, pipeline network rehabilitation + construction

Client

illwerke vkw AG

Project description

The drinking and process water supply for the Obervermuntwerk I and II hydroelectric power plants of the illwerke vkw AG was renovated in 2019 and 2020 to bring it up to the latest state of the art. Renovation was necessary to ensure smooth operation of various parts of the power plant and to ensure the supply of sanitary and catering facilities with water while maintaining maximum operational safety.

 